Oftentimes, construction contract disputes arise because two parties to a contract disagree over the interpretation of a provision that is supposed to govern a specific event or circumstance.
Dodging the drafter
Language in a contract is considered ambiguous if it is subject to two or more reasonable interpretations. It is not enough that two parties differ on the meaning of the language—both meanings offered by the parties must be reasonable ones. When confronted with ambiguous language, the court must determine what the parties supposedly intended when they entered into the contract.
As a preliminary matter, a contractor can only challenge a “latent” ambiguity—one that is initially unambiguous on its face, but which becomes unclear only upon closer examination or after the occurrence of an event or circumstances. If the ambiguity is “patent” or obvious, the contractor has a duty to bring the ambiguity to the owner’s attention before submitting its bid, and failure to do so means it has assumed the risk that its interpretation is the correct one.
Most contractors are aware of the rule that ambiguities are resolved against the drafter, which is often the owner. Most contractors are surprised to learn, however, that this is a rule of last resort and will be applied only after the exhaustion of other efforts to ascertain the parties’ intention.
The court will avoid reading one provision in isolation and will typically consider any other provisions in the contract that might bear on the same subject matter so as to give meaning to the contract as a whole. This occurs most often when multiple technical specification sections govern a particular part of the work and one section might modify, illuminate or even limit other sections.
Courts also will look at documents that evidence or memorialize pre-contract discussions or negotiations such as an original offer, a quotation or meeting notes. In the public contracting sector, these documents rarely come into play because contracts are competitively bid and no negotiations take place. However, pre-bid meeting minutes have been used for this purpose. In addition, negotiations do occur in connection with change orders, and the meaning of change-order language sometimes becomes the subject of disputes. A party might prevail if it can produce notes or worksheets created during change-order negotiations that corroborate its version of what the parties intended.
Courts will similarly look to any inconsistencies between a party’s interpretation of the contract and their own conduct on the same project. In some instances, a court might even look to what is customary in the industry to aid it in resolving a contract ambiguity. This occurs when contract language uses terms specific to the industry. To illustrate, a court recently permitted a contractor to introduce evidence at trial on the industry meaning of “working day” when the contract used the term, but did not provide a definition.
Only if the court is unable to resolve the ambiguity after considering all of the above will it apply the last resort rule and construe the language against the drafter.
One line of caution: In a few states such as Oklahoma and North Dakota, the last rule cannot be applied against a public owner because it has been determined to conflict with public policy. In real practice, contractors should be aware that the most cited rule of construing ambiguous contract language against the party who drafted it is rarely applied. In most instances, courts are able to resolve such disputes by considering the factors cited above and determining the parties’ original intention.
More like this
Roads&Bridges Videos
Industry News
Products
4472 Products
-
The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format. The FVT/...
-
RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
-
Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
-
Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
-
JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
-
Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
-
The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
-
Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
-
The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
-
Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...