No. 3 - Henry G. Gilmerton Bridge

Dec. 15, 2014
Coast Guard regulations force Virginia to construct a spanning success

When it came time to replace the Henry G. Gilmerton Bridge in the Hampton Roads region of Virginia in 2009, the project team had very strict parameters to work within. The span is one of five critical crossing points for the Elizabeth River in the region, resulting in major vehicle and boat traffic for the port area. Consequently, Virginia DOT required the bridge to stay open throughout construction. Modjeski & Masters examined several alternatives, including moving the bridge north or south, but the Coast Guard was adamant the new bridge had to be on the same alignment as the original structure. Added to which, a 100-year-old railroad bridge owned by Norfolk Southern sat just 25 ft to the south of the Gilmerton Bridge.

All of these constraints led to one reasonable conclusion: building a vertical lift bridge directly on top of the old span. “The tight site conditions drove everything else on this project, forcing some decisions that wouldn’t have been made on other projects,” Kevin Johns, deputy project manager for Modjeski & Masters, told Roads & Bridges.

To minimize disturbance to all of the surrounding structures, the project team installed eight 12-ft-diam. drilled shafts with steel casings to support the new span. Finding bedrock in which to plant the shafts was difficult due to the bridge’s location in the Great Dismal Swamp. Extensive geotechnical studies determined each shaft had to penetrate 120 ft below sea level, twice as deep as the old bridge’s foundations. This required a special oscillating crane attachment from German manufacturer Leffer.

“Cases of this size had never been oscillated before,” said Johns. Keeping vibrations to a minimum so as not to disturb the railroad bridge was paramount, so crews kept a close eye on seismic indicators and achieved their goal.

The new main spans were a towering 207 ft tall, every inch of which was required to achieve the needed 135 ft of vertical clearance.Once the new span was complete, the project team did a “float-in, float-out,” putting the old bridge on temporary supports while cutting it free and floating it out. At that point, the new bridge was floated in on barges and settled onto its supports. 

Norfolk Southern allowed VDOT to use some of its right-of-way for the railroad bridge to expand the Gilmerton Bridge from four lanes to six. R&B

PROJECT: GILMERTON BRIDGE REPLACEMENT
LOCATION: CHEASPEAKE, VA.
OWNER: VIRGINIA DOT
DESIGNER: MODJESKI & MASTERS
CONTRACTOR:
PCL CIVIL CONSTRUCTORS INC.
COST: $134 MILLION
START DATE: NOVEMBER 2009
COMPLETION DATE: AUGUST 2014

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Powerful Concrete Protection For ANY Application

PoreShield protects concrete surfaces from water, deicing salts, oil and grease stains, and weather extremes. It's just as effective on major interstates as it is on backyard ...

Concrete Protection That’s Easy on the Environment and Tough to Beat

PoreShield's concrete penetration capabilities go just as deep as our American roots. PoreShield is a plant-based, eco-friendly alternative to solvent-based concrete sealers.

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.