Printer-friendly versionSend to friend
Thursday, August 14, 2008 - 10:19
Need it altered?

When a contractor encounters differing site conditions on a project, an equitable adjustment for additional costs and/or time can more often than not be justified under either the Differing Site Conditions or Changes in the Work contract provisions.

State policed

According to federal law, every state highway construction project approved for federal funding must include certain provisions in the contract between the state highway department and the contractor. Of these, the most relevant are the Differing Site Conditions (DSC), Suspension of Work and Significant Changes in the Character of the Work (Changes) provisions. The statute prescribes specific language for each contract clause, but provides limited flexibility to state highway departments to omit any of the three provisions or to use alternative language, but only if specifically mandated by state law.

To illustrate, pursuant to state law, the North Carolina Department of Transportation has eliminated the DSC clause from its contracts and purports to place on the contractor the risk that actual conditions differ from those represented in geotechnical data the department provides or from those conditions ordinarily encountered.

The federally mandated Changes clause states that the contractor is entitled to an equitable adjustment “[i]f the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character . . .” This means that a contractor is entitled to recover its increased cost of performing any work that is significantly changed and any increased cost incurred performing other work that, while not physically altered, is nevertheless affected by the changes. The latter is typically referred to as “changes to the unchanged work.”

Conversely, the federally mandated DSC clause contains the following final sentence: “No contract adjustment will be allowed under this clause for any effects caused on unchanged work.” Immediately following this language in the statute is a parenthetical that expressly allows state highway departments to omit the last sentence, thereby giving to each state the flexibility to decide whether or not contractors encountering differing site conditions will be compensated for changes to the unchanged work. Accordingly, in some states, contractors encountering differing site conditions are paid for changes or impacts to the unchanged work, and in other states they are not.

Change sense

Given the linear nature of highway construction and the importance that time and resources play in determining the success of a project, little room for error exists. For example, a significant delay or additional work added to a heavy excavation operation is likely to affect the installation of storm drainage. Similarly, if the progress of a contractor’s subgrade preparation operation is adversely affected by unanticipated conditions, its aggregate placement or paving operations will likely be altered. For this reason, only the most minor changes or insignificant differing site conditions will have no impact on other “unchanged work.” In fact, it is entirely possible that impact costs could greatly exceed the costs incurred performing the changed work.

Contractors must be aware of which approach their particular state highway department has chosen. If the DSC clause does not expressly exclude costs incurred performing unchanged work, the contractor can expect to be treated the same as if a change in the work occurred. Otherwise, upon discovering differing site conditions, the contractor should develop a strategy of consistently addressing the matter as a change in the work and should formally seek an adjustment under the Changes clause.

Roads&Bridges Videos

 

Industry News

The Ohio Department of Transportation (ODOT) is hoping to generate millions of dollars in new money by launching a program that will permit...
As the people in and around Atlanta prepare to decide on a sales-tax referendum that could generate $6.14 billion for transportation upgrades,...
Utah’s S.R. 92 project should have been completed in late 2011, but traffic cones are still visible. Now the state legislature is telling the Utah...

Products

3259 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...