When a contractor encounters differing site conditions on a project, an equitable adjustment for additional costs and/or time can more often than not be justified under either the Differing Site Conditions or Changes in the Work contract provisions.
State policed
According to federal law, every state highway construction project approved for federal funding must include certain provisions in the contract between the state highway department and the contractor. Of these, the most relevant are the Differing Site Conditions (DSC), Suspension of Work and Significant Changes in the Character of the Work (Changes) provisions. The statute prescribes specific language for each contract clause, but provides limited flexibility to state highway departments to omit any of the three provisions or to use alternative language, but only if specifically mandated by state law.
To illustrate, pursuant to state law, the North Carolina Department of Transportation has eliminated the DSC clause from its contracts and purports to place on the contractor the risk that actual conditions differ from those represented in geotechnical data the department provides or from those conditions ordinarily encountered.
The federally mandated Changes clause states that the contractor is entitled to an equitable adjustment “[i]f the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character . . .” This means that a contractor is entitled to recover its increased cost of performing any work that is significantly changed and any increased cost incurred performing other work that, while not physically altered, is nevertheless affected by the changes. The latter is typically referred to as “changes to the unchanged work.”
Conversely, the federally mandated DSC clause contains the following final sentence: “No contract adjustment will be allowed under this clause for any effects caused on unchanged work.” Immediately following this language in the statute is a parenthetical that expressly allows state highway departments to omit the last sentence, thereby giving to each state the flexibility to decide whether or not contractors encountering differing site conditions will be compensated for changes to the unchanged work. Accordingly, in some states, contractors encountering differing site conditions are paid for changes or impacts to the unchanged work, and in other states they are not.
Change sense
Given the linear nature of highway construction and the importance that time and resources play in determining the success of a project, little room for error exists. For example, a significant delay or additional work added to a heavy excavation operation is likely to affect the installation of storm drainage. Similarly, if the progress of a contractor’s subgrade preparation operation is adversely affected by unanticipated conditions, its aggregate placement or paving operations will likely be altered. For this reason, only the most minor changes or insignificant differing site conditions will have no impact on other “unchanged work.” In fact, it is entirely possible that impact costs could greatly exceed the costs incurred performing the changed work.
Contractors must be aware of which approach their particular state highway department has chosen. If the DSC clause does not expressly exclude costs incurred performing unchanged work, the contractor can expect to be treated the same as if a change in the work occurred. Otherwise, upon discovering differing site conditions, the contractor should develop a strategy of consistently addressing the matter as a change in the work and should formally seek an adjustment under the Changes clause.
Roads&Bridges Videos
Industry News
Products
-
Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
-
The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
-
The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
-
Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
-
Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
-
Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
-
Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
-
BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
-
American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
-
The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...









