Highway contractors and other public contractors are intimately familiar with formal claims processes and the attendant pitfalls along the way that are mostly designed to protect the public entity but sometimes are used as a sword by public entities to invalidate otherwise legitimate claims. Another area of concern—especially for lawyers who are brought in at a later date and asked to file suit—involves how closely the allegations of the lawsuit must mirror what the contractor contended in the claim that was submitted to the public entity. A recent case decided by the U.S. Court of Federal Claims provides some relief to that concern.
Included are the facts
In DeAtley Construction Inc. v. U.S., a contractor performing a project for the Federal Highway Administration (FHWA) on government-owned land was responsible for placing aggregate base on a roadway that would be paved by others at a later date. The contractor also was responsible for producing the aggregate in accordance with the project specifications from a rock borrow area the government supplied.
The contractor produced and stockpiled all aggregate in 2001 and returned to the project the following year to place it. After completing a portion of the roadway, the contractor discovered that the aggregate had degraded and thus would not pass the prescribed tests. The contractor offered to provide FHWA with a credit of $21,425, or 25% of the contract price, rather than replace it with new aggregate, but FHWA declined and ordered the contractor to remove and replace the aggregate with new aggregate. The contractor did so and then filed a claim seeking additional compensation for the costs associated with the added work.
In the claim, the contractor recited the facts in support of entitlement and adequately set forth its claimed damages. The FHWA denied the claim, and the contractor filed a six-count complaint against the government. The government contended that since the contractor argued only differing site conditions in the claim it submitted to the contracting officer, the court had no jurisdiction to consider other counts contained in the lawsuit for breach of contract, defective specifications, constructive change and economic waste.
The court observed from prior cases that a contractor’s claim to the government need not be in “any particular form or use any particular wording,” but it must provide “a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” In this regard, the court held that the complaint filed in the lawsuit need not set forth the same legal theories identified in the claim so long as they “arise from the same operative facts” and “claim essentially the same relief” as the underlying claim previously submitted to the government.
The court then set out to determine whether the claim the contractor presented to the government contained all facts necessary to support each of the four legal theories in question. The court concluded the facts necessary to support those legal theories were included. On the other hand, it determined that the contractor failed to set out in the claim all of the crucial facts supporting defective specifications. Consequently, the court dismissed the count for defective specifications, but allowed the other three counts to remain.
The DeAtley case is a favorable one for contractors because it rejects the notion that a contractor’s lawsuit must be a mirror image of the claim submitted to the government for decision. However, the case also serves as an impetus to contractors to closely consider all potential legal theories.
More like this
Roads&Bridges Videos
Industry News
Products
2112 Products
-
The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format. The FVT/...
-
RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
-
Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
-
Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
-
JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
-
Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
-
The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
-
Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
-
The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
-
Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...









