Printer-friendly versionSend to friend
Tuesday, April 16, 2002 - 09:29
Full cooperation

All facets of the industry come together to meet tight deadline of I-25

Calling it “a big project” would be an understatement—because it is bigger than that, much bigger. Try this on for size:

The Big I Reconstruction Project in Albuquerque, N.M., involves more than 2 million cu yd of dirt, 610,000 tons of hot-mix asphalt (HMA) and 165,000 cu yd of concrete. And all of it is being used to rebuild two interstate highways (I-25 and I-40) that happen to cross each other in the middle of a busy metropolitan area.

But the really big things that have emerged from the Big I
Project are imagination, determination and a willingness to cooperate on the
part of everyone involved. This job was presented to the contractors with a
time frame that many people thought was absolutely impossible: just 24
months—June 2000 until June 2002—from start to finish.

Along the way, industry observers saw one other interesting
intangible emerge. The government officials and contractors decided early on to
set aside any predisposition or favoritism they might have toward the two
traditionally competing construction materials, asphalt and concrete. Instead,
they agreed to let each of the materials do the job it was best designed to do.
The concrete was used for building 45 segmental and structural-steel bridges,
and the asphalt was used to pave the project—a total of 111 lane miles of
roadway.

With only 24 months to complete the $270 million project,
speed and efficiency were absolutely critical to the Big I Project. From the
very beginning, it was determined this was to be a fast-track project. Indeed,
the time line was so compressed that many officials thought it was overly
ambitious and that it could not be finished on time.

Beyond repair

The Big I intersection was originally designed more than 50
years ago to serve as part of the nation’s defense system, as well as
speeding and facilitating the flow of interstate commerce. Two major interstate
highways—I-25 (Pan American Freeway) and I-40 (Coronado
Interstate)—were to cross just north of the downtown area of Albuquerque.
When it was finished in 1966, the Big I intersection accommodated fewer than
40,000 vehicles each day. By 1970, the traffic had doubled. And today, more
than 300,000 vehicles travel through the Big I in a single day.

Thirty-five years of increasingly heavy traffic had brought
the Big I intersection to the end of its useful life. Officials with the New
Mexico State Highway and Transportation Department (NMSHTD) considered
repairing the roadways, but rejected that idea when it was estimated that the
cost to repair and maintain the existing system would be more than $70 million.
It also would be expensive in terms of taxpayer irritation since repair would
require about six years of sporadic road closures and traffic rerouting.
Additionally, there were a number of traffic-safety issues: the original design
used a number of left-hand exit and entrance ramps connecting the two
interstates.

The decision was made to totally redesign the intersection
of the two interstates to reflect the latest in highway-design technology and
traffic-safety protocols.

Pile it on

The original Big I interchange had been designed to last for
about 20 years—or until 1986—and it was obviously not going to be
able to handle the traffic loads of the next decade or two. The new de-sign
incorporated innovations that would smooth the flow of traffic, increase driver
safety and provide good service far into the future. The engineering team came
up with an interchange design that called for 45 new bridges (instead of 15 on
the original intersection) and 111 lane miles of roadway (instead of 17 lane
miles on the original). And all of this would take place within a 1-mile radius
of the Big I intersection.

Since 90% of the traffic on the Big I intersection is local,
the engineers had to provide entrance and exit ramps at major thoroughfares, as
well as frontage roads between those entrance/exit points so drivers could
readily access destinations. With this complex web of freeways and frontage
roads running, literally, in all directions, it was necessary for the engineers
to think in terms of three-dimensional space: multiple levels of roadways would
be required to achieve the desired traffic patterns. This would require
numerous “fly-overs,” or bridges that carried traffic over other
roadways. In its final design, the Big I intersection ended up with five different
levels near the central part of the complex. From the surface of the
bottom-most roadway to the surface of the uppermost fly-over, the vertical
distance is more than 70 ft.

It quickly became obvious that a project of this magnitude
was going to require a lot of time, a lot of money and a lot of patience. Most
observers estimated that demolishing the old roadways and bridges and building
new ones would require a construction cycle of between four and six years, and
it would probably end up being closer to six years.

Just a couple more

Early in the planning stage, everyone involved in the
project was asking the same question: “Where do we start on a project
like this?” Nothing like this had ever been done in New Mexico. Perhaps
nothing like this had ever been done anywhere in the world, because the
planners were determined that traffic through the area would not be totally
closed down at any time during the reconstruction. The roadways were too
critical to both local traffic and over-the-road transport.

One other fact emerged from the initial discussions between
city officials, engineers from the NMSHTD and administrators from the Federal
Highway Administration (FHWA): The taxpayers would not tolerate an extended
period of construction with confusing shutdowns, complicated traffic rerouting
and endless traffic delays. Whatever plan they were to come up with had to
assure a speedy construction cycle. According to Pete Rahn, secretary of the
NMSHTD, “We decided that six years was out of the question. And so was four
years. Consequently, we set out to get the job done in just two years. We
thought the driving public could probably handle that.”

High start

It soon became apparent that the best way to approach this
project was to rebuild the intersection from the top down: the highest ramps
and fly-overs were built first, the middle-level ramps were built next and this
was followed by finishing up the frontage roads. This “top-down”
approach would permit the maintenance of traffic at the existing ground-level
roadways while the major bridge-building activity took place above them. The
contractor would proceed with construction simultaneously on all four legs of
the intersection.

Work would take place six days a week in two 9-hour shifts
each day. On any given day, two lanes of both freeways were to remain open to
traffic during daytime hours. Only at night (between 9 p.m. and 5:30 a.m.)
would the contractor be allowed to totally close a section of the freeway.
Maintaining good traffic flow and positive public opinion was a part of job
performance that all parties accepted as mandatory from the very beginning.

Long on supplies

Given the many constraints on this project, the selection of
the right materials for each part of the project was a matter of critical
importance. The 55 new or renovated bridges that were involved in the Big I
Project would be built using concrete because of that material’s inherent
structural strength when combined with steel reinforcing bars and cables. Ten
of the original bridge structures would remain after being rehabilitated. There
would be 37 new prestressed concrete and steel-girder bridges, and there would
be eight precast concrete segmental bridges with a total of 663 different
built-to-fit segments.

For the paving between the bridge structures, however, the
engineers chose to go with multiple lifts of HMA with Superpave designations
SP-2 and SP-3. The project would involve about 610,000 tons of asphalt to pave
the 111 lane miles of freeway and frontage roads. About half of that would be
base-course material and the other half would go into the finish lifts.

According to Reuben Thomas, division administrator with the
New Mexico Division of the FHWA, the engineers initially picked asphalt as the paving
material of choice because it was more cost-effective.

“We did a cost analysis,” said Thomas. “We
were trying to do several things: keep the cost down and still get a long
service life. We also looked at the project’s critical path, and so speed
of construction also came into consideration. In all of these considerations,
asphalt came out on top.”

Thomas said asphalt also worked out to be more economical
than the traditional alternative, concrete. “Through value
engineering,” he said, “we found that the initial cost of asphalt
is lower. We also decided that using asphalt as our paving material was the
only way to maintain the flow of traffic and give the contractor the
flexibility he needed.”

Thomas said the history of the project has proven their choice
of asphalt to be the right choice. “We are ahead of schedule at this
point, and we are confident that the project will be completed at least a month
ahead of schedule. We also are within budget, so our decision to use asphalt is
being validated now.”

Any speeders interested?

The general contractor and project manager on the Big I
Project is Twin Mountain Construction Co., a subsidiary of Peter Kiewit Sons
Inc. The New Mexico-based contractor was chosen to handle both the HMA paving
and the bridge construction.

According to Van Groves, president and chief executive
officer of Twin Mountain, one of the most formidable challenges on this project
was the two-year time frame from start to completion.

“When the highway department was letting this
project,” said Groves, “they wanted only people who were truly
interested in getting it built in 24 months. They weren’t interested in
anyone who wasn’t going to take that deadline seriously. The only
contractors they wanted bidding on this job were those contractors who were
committed to meeting that deadline.”

Groves said this particular project has made history in how
fast-track construction can be managed. But even more important, it has set new
benchmarks in how all parties involved in a project can work together closely
in order to achieve “impossible” goals.

“Almost everyone in the industry talks about
‘partnering’ from time to time,” said Groves. “But on
this job, everyone actually does it. No matter where you look, you will find
very high levels of teamwork: from the department of transportation to the
Federal Highway Administration to the design-engineering firm to the contractor
and subcontractors. Everyone involved in this project is really living and
breathing partnering.

“Personally,” Groves continued, “I give
the highway department the most credit for their commitment. They said they
were going to do it. They committed themselves to doing it. And they are doing
it. We’re just the contractor; we can’t make them do it. We could
have a hundred partnering teams, but nothing substantive would happen if the
highway department didn’t make it happen. They are the reason this
project is all coming together so successfully.”

According to Pete Rahn, secretary of NMSHTD, the rebuilding
of the Big I intersection required an extremely high level of cooperation and
teamwork between all agencies and groups involved: NMSHTD, FHWA, the city of
Albuquerque, Bernalillo County, the contractors, the business community, the
trucking industry, the local safety and emergency agencies, the media and the
individual commuters.

“On this project,” said Rahn, “we have
broken new ground in terms of the partnerships we have formed and the
cooperation we have received. There has been a spirit of mutual trust, respect
and a willingness to work together to do whatever it takes to get the job done.
This project will become the signature model for highway building
everywhere—not just in New Mexico, but across the country.”

In June 2001, all of the parties involved celebrated
reaching the halfway point in the project, five months later the work was
progressing ahead of schedule. They now estimate that the project will be
completed in May 2002—about a month ahead of the original deadline.

Roads&Bridges Videos

 

Industry News

The two-year transportation bill pushed by the Senate could be one step closer to a Congressional showdown if it receives enough votes necessary for...
Federal Highway Administrator Victor Mendez yesterday reviewed preparations for the construction of the new Memorial Bridge connecting Portsmouth, N....
Metro Detroit public transit advocates are embroiled in a battle for improved bus service this year as the city and suburban bus systems slog through...

Products

  • Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
  • The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
  • The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
  • Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
  • Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
  • Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
  • Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
  • BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
  • American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
  • The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...