Friday, February 3, 2012 - 11:30
Denver stormwater authority quickly repairs damaged culverts

The Southeast Metro Stormwater Authority (SEMSWA), located in the south metro Denver, Colo., area, is responsible for several culverts located throughout many residential neighborhoods. After evaluating the culverts, SEMSWA determined that multiple culverts were damaged and needed to be replaced.

 

Besides being located in a residential neighborhood, the area containing the culverts also was considered a protected wetland and residential park. Therefore, this area could not be disrupted and care had to be taken not to affect the water quality.

 

Since digging and replacing the damaged corrugated metal pipe (CMP) culverts would severely inconvenience the local residents, potentially harm the wetland area, and cripple the already small SEMSWA budget, a solution was needed to quickly and cost-efficiently replace the pipe.

 

SEMSWA decided to use Snap-Tite pipe and purchased 80 linear feet of 30-in. Snap-Tite pipe for three scheduled projects to reline the old culverts.

 

The first reline project served as a demonstration where other government agencies were invited to watch. Attendees included representatives from the Colorado DOT as well as some local contractors.

The SEMSWA crews were able to quickly move the 30-in. pipe in place for lining the CMPs using a mini excavator. For each of the culverts, one section of pipe was slid inside the old culvert. Then the next section was snapped on using a come-along and chains. This process was repeated for each culvert until the liner was in place from end to end. Finally, grout was used to fill in any annular space between the old wood culverts and the new pipe liner.

 

The SEMSWA maintenance supervisor, Bob Winzent, commented that the installation made it easy for them to fix their culverts on short notice.

 

The culvert lining system was a no-dig solution that rehabilitated the culvert without shutting down the road and disturbing either the residential traffic or the protected wetland area.

Slideshow

  • For each of the culverts, one section of pipe was slid inside the old culvert. Then the next section was snapped on using a come

Roads&Bridges Videos

 

Products

8819 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...