Printer-friendly versionSend to friend
Thursday, December 28, 2000 - 08:17
CONCRETE SOLUTIONS

The race for progress

The race for progress
Researchers at the University of California-Berkeley have documented a remarkable reconstruction project on I-10 in California—2.8 lane-km of concrete pavement was replaced in 55 hours over one weekend by the Morrison-Knudsen Corp (see Driving after 55; team races through job, January, 2000, p 23). The work involved the following: lift out and haul away slab segments previously sawcut; clean cement-treated subbase; install tiebars and dowels; place, finish and texture new concrete; cure four hours; saw joints; and open to traffic.
The segment of I-10 running through southern California, commonly called the "San Bernardino Freeway," was built in the early 1960s for a 20-year design life. Traffic volumes in this stretch of freeway, are as much as 240,000 ADT.
The objectives for the I-10 Pomona project focused on documentation of the traffic management plan and construction process for both nighttime and weekend closures, to document the techniques the contractor used to reconstruct the urban concrete pavement and to identify which construction areas were constraining the overall project productivity. Identification of the constraining activities could help improve future construction productivity by allowing contractors and agencies to focus on innovations in a particular area.
The rehabilitation project used fast-track concrete with four-hour curing time and two different construction windows (i.e. one 55-hour weekend lane closure and a series of repeated nighttime closures [7 and 10 hours]), and was completed successfully. This indicated that state agencies should be confident that 3 lane-km of pavement reconstruction on a weekend is an achievable goal.
The average production rates showed that weekend closures were 55% more productive than nighttime closures.
The overall progress of the project was found not to be controlled by the demolition activities; the maximum amount of the demolition under the contractor’s process for 55 hours of work could have been 5 lane-km. Concrete delivery to the site was found to be the constraining factor.
If the initial paving progress was maintained throughout the project length and no breakdowns occurred, the maximum amount of the rehabilitation which could be completed within a 55-hour weekend would be 3.5 instead of 2.8 lane-km.
These results may facilitate effective technology transfer to other agencies, contractors and elected officials.

Roads&Bridges Videos

 

Industry News

A piece of federal legislation in the works is making Chicago transit directors very nervous, according to the Chicago Tribune.   The...
The two-year transportation bill pushed by the Senate could be one step closer to a Congressional showdown if it receives enough votes necessary for...
Federal Highway Administrator Victor Mendez yesterday reviewed preparations for the construction of the new Memorial Bridge connecting Portsmouth, N....

Products

  • Husqvarna’s FS 9900 D 3-speed gearbox flat saw works for jobs that require deep cutting or high production rates. Its fifth wheel option helps raise...
  • The new John Deere 9RT Scraper Special Series Tractors provides improved productivity, increased uptime and lower operating costs. This new series,...
  • The U.S. Environmental Protection Agency (EPA) recently designated the ClearLane enhanced deicer with a Design for the Environment label. In the new...
  • Lindsay Transportations Solutions added the TAU-II-R system to their lineup of road safety devices. Utilizing reusable elements, the system will...
  • Plastic Safety Systems Inc. recently introduced RoadQuake 2, its newest temporary portable rumble strip. Suitable in even sub-freezing temperatures...
  • Build tall, reinforced retaining walls with 100% positive connections using the Redi-Rock Positive Connection (PC) System. Incomparable structural...
  • Color-Safe Surface is an acrylic-based material used for pavement markings. It is typically used for bicycle and bus lanes, pedestrian areas,...
  • BOMAG’s BW 900-50 is the company’s latest generation 1-1.5 ton ride-on roller. Offering a working width of 35.4 in. and Honda’s GX630 gas engine, the...
  • American Highway’s Inclined Pivoted Turnbuckle Manhole Riser allows the user to not only raise the lid, but also tilt the lid to match the new road...
  • The Schwing S 43 SX concrete pump combines the best features of two boom types: Roll and Fold and Z. By putting the 270º Z-fold at the tip section,...