Printer-friendly versionSend to friend
Tuesday, July 14, 2009 - 11:19
Check changes

The changes clause is intended to provide flexibility in the event alterations in the work are necessary to ensure that the finished project functions as the owner originally intended. But does this clause give the owner unfettered authority to add or delete work as it sees fit? As an appeals court in Georgia decided, the answer is no.

Grey grassy area

In Savannah Airport Commission v. Higgerson-Buchanan, Inc., 519 S.E.2d 475 (Ga.App. 1999), the prime contractor entered into a unit-price contract for expansion of an airport. The prime hired a subcontractor to perform clearing and grubbing of over 500 acres. In its bid, the prime simply took the subcontractor’s unit price per acre and added its markups.

The subcontractor’s bid price per acre was a weighted average of several individually estimated prices because approximately 28% of the clearing area was heavily wooded; 41% was lightly wooded; 13% involved swamp land; and 18% was grassy area. The problem occurred when nearly all clearing except the least-costly grassy area was complete.

The owner apparently did not realize that its engineer had included the grassy areas in the acreage applicable to the “clearing and grubbing” bid item. Accordingly, when viewed in isolation, the price the owner was paying for grubbing the grassy areas appeared excessive. To avoid paying the clearing and grubbing unit price for the grassy areas, the owner relied upon the changes clause to delete the remaining clearing work from the contract and insisted that the grubbing necessary to remove the grass was incidental to excavation work.

The court disagreed with the owner’s position and determined that the changes clause applies only to those changes within the general scope of the original plans and specifications and necessary to complete the work originally contemplated by the contract. More specifically, the court held that the changes clause cannot be used to delete work that is still necessary in order to complete the project.

Owner is not cleared

In this case, the court determined that the owner’s motivation to secure an economic advantage was improper, especially since the inclusion of the grassy area within the total clearing acreage had the effect of lowering the overall contract unit price for clearing. Significantly, the court determined that the owner never intended to delete the grassy area from the scope of the project.

It was merely trying to avoid application of the clearing and grubbing unit price to that area. By doing so, the owner would have denied the contractor and its subcontractor the opportunity to realize the profit they had built into the overall unit price for clearing and grubbing.

When confronted with an owner’s attempt to delete work from a contract, project personnel should read carefully the applicable changes clause to confirm that changes under the clause must be “necessary” or “to satisfactorily complete the project.” Next, they should try to determine the owner’s reason for seeking to delete the work. If the purpose of the change falls outside the scope of the changes clause or is otherwise suspect, project personnel should consult with upper management or legal counsel immediately so that a timely determination can be made whether to challenge the owner’s directive.

Roads&Bridges Videos

 

Industry News

Utah’s S.R. 92 project should have been completed in late 2011, but traffic cones are still visible. Now the state legislature is telling the Utah...
The latest national traffic signal assessment conducted by the National Transportation Operations Coalition (NTOC), a group of transportation...
The cost of construction materials took a breather in April, while contractors showed slightly greater ability to roll past price increases into...

Products

2933 Products

  • The ComNet FVT/FVRHDMI transmits a high-resolution HDMI signal over one multimode fiber up to 500 meters for the 1080p60 format.  The FVT/...
  • RTMS (Remote Traffic Microwave Sensor) is a non-intrusive, radar-based detection system renowned for long-term, worry-free reliability and...
  •   Volvo almost completely redesigned its B-Series of backhoe loaders, which includes the BL60B and BL70B. Among the changes is a new set of...
  •   Maximizing productivity and efficiency is the key to the eight models in John Deere’s K Series of backhoe loaders, which also features a pair...
  • JCB has extended the reach, both literally and figuratively, of its ICX backhoe loader with longer loader arms (by 4 inches) and an extending dipper...
  • Allowing man and machine to work together more efficiently was the goal of the upgrades to Terex’s TLB 840 backhoe loader, starting with the...
  • The C Series from New Holland Construction offers the B95C LR (long reach) and the B95C TC (tool carrier). The LR is more compact with a longer stick...
  •   Case’s N Series of loader backhoes — which includes the 580N, 580 Super N, 580 Super N Wide Track and 590 Super N — are driven by Tier 4-...
  • The Cat C4.4 engine on the three new models in the F Series — the 416F, 420F and 430F — upgrades power while staying up to Tier 4 Interim emissions...
  •   Versatility is the name of the game with the L45 Tractor-Loader-Backhoe from Kubota, a 3-in-1 machine with a 45-hp Kubota diesel engine at its...