Highway reconstruction can devastate intelligent
transportation systems, which often depend on underground cabling for
communications.
With more and more large-scale ITS deployments occurring
around the country, a new challenge facing highway engineers is keeping those
systems running during roadway con- struction or rehabilitation projects. Many
systems, such as the Northern Virginia Traffic Management System, also serve
critical regulatory functions, such as controlling access to reversible lanes
of interstate roadway, and can tolerate very little down time.
This article explores methods that were used to keep ITS
equipment operational and to manage traffic congestion during a major
interchange reconstruction and details the lessons that were learned in the
process.
The Northern Virginia Traffic Management System (TMS) is a
computerized highway surveillance and control system that manages traffic along
I-95, I-395, I-495 and I-66 in the Washington, D.C., area. The original system
was constructed in the early 1970s and has since been expanded to cover a
combined distance of 65 miles using an underground fiber optical cable
communications system. The Virginia DOT controls the system from their
“Smart Traffic Center” in Arlington, Va.
TMS operators and maintenance personnel cringed at the
announcement that one of the area’s most notorious interchanges, the
Springfield Mixing Bowl, would soon be reconstructed. Located about 15 miles
south of Washington, D.C., the interchange sat directly over one of the
TMS’ main trunk cables, which carried signals to approximately 25 CCTV
cameras, 15 access control gate sets, 70 VMS and 60 detector stations on I-95.
Dubbed “The Interchange from Hell” by the Wall
Street Journal, the Springfield Mixing Bowl carries 400,000 vehicles per day on
14 lanes that mix three interstates and one state highway together in a
3/4-mile span.
In addition to severing trunk communications, the
reconstruction also would affect several traffic management devices within the
interchange.
Another major concern to VDOT officials was managing traffic
congestion during construction. Public acceptance and support for the new
roadway interchange were critical given the major inconvenience that
constructing the roadway would pose. VDOT awarded a design contract to HNTB
Corp. for all aspects of the civil and ITS design, as well as the development
of a congestion management program to limit the negative impacts the
reconstruction would have on the area’s many commuters.
Maintaining existing equipment
Maintaining the existing equipment throughout the
construction period was a daunting task. The trunk lines were scheduled to be
severed during the first few months of the roadway construction, which meant
several ITS-related activities fell on the critical path. These activities
included rerouting the main trunk cable around the interchange, installing
wireless communications to the existing equipment and implementing temporary
equipment to replace existing devices that could not be maintained. Much of the
existing and temporary equipment would then be replaced with new, more modern
equipment as the final roadway took shape. The rerouting of the trunk cable and
the installation of the wireless communications equipment and temporary field
devices made up what came to be known as the Interim Traffic Management System.
The Interim System would operate during the final construction of the
interchange and then be replaced almost entirely by a Final System, which would
communicate over a new fiber-optic cable installed as part of the
reconstruction.
Perhaps the biggest challenge was maintaining communications
to the myriad of equipment installed along I-95 over 19 miles south of the
interchange. This meant re-routing the fiber-optic trunk cables around the
interchange to the Smart Traffic Center (STC). Other communication alternatives
were considered, including long-haul microwave links between each of three communication
hubs and the Smart Traffic Center.
In the end, it was the reliability of maintaining a fiber
link to the STC that influenced the decision to attempt what seemed to be a
difficult and costly rerouting of the fiber. Installing the rerouted cable
along arterial roadways and adjacent railroad right-of-way were promising
options early in the design; however, a fiber installation on an adjacent
corridor by a federal agency proved to be a coincidental stroke of luck. A
resource sharing agreement was made that involved the federal agency’s
contractor installing a dedicated fiber-optic cable for the TMS, bypassing the
interchange entirely.
This contractor also was asked to run a spur off this cable
to the top of a 15-story building adjacent to the interchange called the
Springfield Tower. This cable would provide a link between wireless receiving
equipment installed in the rooftop of the tower and the STC, providing a
valuable means to keep existing equipment running throughout construction.
The most critical devices to be maintained within the limits
of the interchange were three sets of gates controlling access to the
reversible roadway lanes. Communications with the gates was not only critical
to opening and closing them at the appropriate times, it also was necessary for
the operation of a safety interlock system that ensured no conflicting gate
sets could be open at the same time. Because continuous multipoint RS-232
communications are required for the interlock system, spread spectrum radio was
chosen to maintain communications to the gate controllers when the interchange
construction severed the existing fiber-optic cable.
In addition to providing information about roadway
conditions, dedicated VMS also are used in a regulatory capacity, controlling
access to the reversible HOV lanes of the roadway. Maintaining control of these
signs was planned using cellular telephone communications over a standard
dial-up connection to the STC. Dial-up connections for the signs were chosen
both for their economy and their simplicity.
Sequence of construction
The sequence in which ITS components were added and removed
from the traffic management system during the roadway construction was
carefully choreographed in order to keep the existing system running while providing
the necessary regulatory control for the reversible HOV lanes. This demanded
careful design coordination among all the civil design aspects of the project.
Every roadway construction activity, such as field grading or the opening of a
detour ramp, had to be analyzed for its effect on the existing TMS and on the
Interim System. For every roadway construction milestone in the project, a
corresponding ITS milestone also was planned to meet the goal of minimal system
down time.
After the reroute of the existing trunk early in the project, the construction
sequence planning focused on the reversible roadway access control gates and
VMS. A number of temporary gates and signs were installed throughout the project
to replace existing equipment demolished by the roadway construction and to
facilitate any shifting or rerouting of HOV traffic during the construction of
the roadway. As traffic was shifted to detours and detour ramps, the temporary
gates and signs were moved accordingly to continue regulating entry to the
reversible lanes.
When a certain amount of down time for the gate controllers
was inevitable at various points during the roadway construction, the
contractor was required to open and close these gate sets by hand.
Congestion management
HNTB and VDOT embarked on an aggressive and comprehensive
congestion management program very early in the project. Four distinct working
groups were set up to explore various congestion relief measures, with each
group reporting to a steering committee consisting of high-level county, state
and federal officials.
The Transportation Demand Management Group explored a
variety of alternative commute programs to give commuters more choices in
avoiding the construction delays.
An Incident Management Group implemented extensive measures
for decreasing incident response times and improving the incident response
capabilities.
The Local Area Network Operations Group examined the local
streets and recommended spot improvements to handle the additional traffic
volume created by motorists diverting to avoid construction.
Finally, a Communications Group worked in concert with
VDOT’s communications director and a private public relations firm to
disseminate commuter information to area motorists. A website
(www.springfieldinterchange.com) was developed providing commuters with
upcoming construction phasing, detour routes and real-time traffic information
to help them make informed decisions about their commuting options.
Lessons learned
With more and more traditional highway and bridge projects
involving a substantial ITS component, significant challenges are being created
for ITS engineers and managers to keep existing systems running and to
coordinate the civil and ITS aspects of the design. With TEA-21’s
emphasis on mainstreaming ITS into general highway funding programs, these
combined projects will become more and more common.
The following lessons learned focus on challenges created by
combining these types of projects.
The relative contract value of roadway construction versus
ITS deployment in these types of combined projects can create numerous problems
in itself. For the Springfield Interchange, the total construction value of the
ITS component of the project was only 5% of the overall contract value.
As such, contractors tended to place little importance on
the ITS aspect of the project, despite the fact that ITS work was on the
critical path. For such projects, the contracting agency is placed at the mercy
of the prime contractor in choosing the subcontractors that work on the job,
because their subcontract bids have little effect on the overall bid price.
The lesson here is to split out as much of the ITS
construction as possible into a separate contract, but keep the ITS and civil
design task intact to ensure that the necessary design coordination takes
place. The designers should determine which parts of the ITS design should be
separated into a distinct ITS contract. The ITS contract should be let as far
in advance of the roadway project as possible.
Another important lesson learned was the value of a
carefully planned sequence of construction. No matter how much ITS work is
accomplished in advance of the roadway construction, complex systems usually
require more ITS work during the roadway construction. TME